Friday, October 23, 2026
During the week of October 26, crews will work in the following areas:
- Lacombe Substation site west of Chestnut Place and 20th Street
- Site preparation and equipment installation
- North corner of Chestnut Place and 19th Street
- Temporary use area
- Staging and storage of equipment and materials
- East corner of Blake and 20th streets
- Temporary use area
- Staging and storage of equipment and materials
- Alley between 20th and 21st streets and between Blake and Market streets
- Temporary equipment and materials staging
- Barker Substation Building on the west corner of 21st and Market streets
- Substation building construction work
- Equipment installation
- 20th Street, between Blake and Market streets
- Sidewalk restoration activities
- North sidewalk closure, pedestrians cross to south side of 20th Street
- South corner of Blake and 21st streets
- Stormwater system installation
- Temporary use area
- Staging and storage of equipment and materials
- Intersection of Larimer and 21st streets
- Underground electric distribution line installation
- Shifting lane closures
- 21st Street, between Lawrence and Larimer streets
- Underground electric distribution line installation
- Shifting lane closures
- Parking restrictions
- Intersection of Lawrence and 21st streets
- Underground electric distribution line installation
- Shifting lane closures
Crews will work Monday through Saturday from 7 a.m. to 7 p.m. In certain circumstances, crews may work evenings, nights, or weekends.
Schedules are subject to change.